ITER installs seventh tokamak module with 5 cm to spare
Image: Interesting Engineering

ITER installs seventh tokamak module with 5 cm to spare

ITER has installed the seventh of the nine sector modules that make up its tokamak, putting the international fusion project more than two-thirds of the way through assembling the machine’s core. The five-storey-tall module was lowered into place on November 25 and 26, leaving only about 5 centimetres of clearance on either side.

The operation took 24 hours and involved a suspended load of nearly 1,400 tonnes, a figure that includes the lifting equipment. ITER said it was the first time teams had set a sector module into a gap between two modules already in position.

A tighter fit than before

Each sector module forms a 40-degree slice of the tokamak’s toroidal vacuum vessel. The module itself weighs roughly 1,100 tonnes and contains a section of the vacuum vessel, its thermal shield and two superconducting toroidal field coils.

In earlier installations, there was open space on at least one side of the suspended module. This time, engineers had to guide the structure down between two neighbours.

The module descended about 30 metres into the tokamak assembly pit. Teams built pauses into the lift so the natural swinging of the load, known as the pendulum effect, could settle before the descent continued.

Tilt sensors, strain gauges and cameras tracked critical clearances and the module’s structural behaviour in real time. Crane operators, engineers, metrology specialists and safety teams worked together to set the component onto temporary supports.

ITER Director-General Pietro Barabaschi said the lift “went exactly to plan”.

Ahead of schedule

ITER said the project is running about six months ahead of the schedule set out in its Baseline 2024 plan. The latest installation follows several recent milestones.

  • The ninth and final vacuum vessel sector arrived on site in October, meaning all major components for the tokamak core are now at the facility.
  • Repair work on the vacuum vessel sectors and thermal shields has been completed, which ITER said reduces technical and scheduling risks for assembly.

What comes next

Two sector modules remain. ITER plans to install them by the second quarter of 2027. Once all nine are in place, assembly teams will align the vacuum vessel sectors and weld them together to form the toroidal chamber that will hold the fusion plasma.

The finished vacuum vessel will measure about 19 metres across and 11 metres high. It will weigh around 5,200 tonnes before internal components are added.

ITER is a collaboration between Europe, China, India, Japan, South Korea, Russia and the United States. The experimental reactor is being built at Saint-Paul-lez-Durance in southern France, with the aim of demonstrating the scientific and technological feasibility of fusion power.