The AI infrastructure build-out is pushing up the price of optical networking equipment and stretching delivery times to as long as 18 months, according to network operator RETN.
RETN said network operators and telcos are now competing directly with AI datacenters for chips and other components. It put the rise in optical equipment prices at around 50% since the start of 2026.
Lead times have multiplied
The bigger problem is delivery. RETN said optical network kit that once arrived within three months now typically takes 12 to 15 months, and some orders are taking up to 18.
Memory prices have also climbed sharply, by four or five times over the past year or so. The current squeeze resembles, and may be worse than, the pandemic-era chip shortages that left network vendors unable to fill orders. This time, the cause is demand outpacing supply as hyperscalers and AI campuses buy up capacity.
In its report, “AI, Connected,” RETN said the surge in demand from AI builders is only one factor. Raw material shortages, a lack of skilled labor, energy constraints, geopolitical tensions and logistics problems are all adding pressure.
RETN also acknowledged that carriers contributed to the situation. Many postponed network upgrades to save money, and that work can no longer be put off.
Customers want more redundancy
RETN said network diversity is now treated as essential. Customers who once accepted two routes to long-haul destinations now expect four or more redundant paths.
The goal is to stop a single failure from knocking out critical services. Extra connections only help if they avoid shared points of failure such as the same ducts or cable routes. RETN said a diverse circuit might cost €1,800 ($1,975) a month rather than €600 ($658), but argued an outage could cost far more.
Datacenters move to remote sites
The report also points to AI datacenters moving away from populated areas toward remote locations, where land, power and water are easier to secure. Hyperscalers are building in the Nordics, which offer affordable land, a cooler climate and plenty of renewable energy.
Those sites often lack the fiber needed to link them with other datacenters and customers. Near cities, developers commonly fund fiber themselves, which adds only a few percent to total project cost. Over longer distances the economics get harder, and carriers are reluctant to build a long-haul route to serve one remote facility.
Some developers are willing to absorb the expense. RETN said a major cloud provider is looking at converting an abandoned factory in Central Europe into a large server farm, even though there is little fiber in the area.
Plan connectivity early
RETN’s advice is that developers building outside established datacenter hubs may need to bring in network carriers two to five years before opening. Connectivity, it said, has to be planned alongside power and construction rather than left until the facility is nearly ready.